|
A Gustav
Story: Dramatic Midnight Mission Reconnects New Orleans-area 'Island' to the
Grid
09/04/2008
Three, two,
one ... those who heard the countdown in person or by phone said you could have
cut the tension with a knife: an engineer called out the sequence to the closing
of an electrical breaker by an operator, toward an uncertain result. At stake:
whether every remaining light in New Orleans would go out.
The breaker closed. Applause erupted, as a
previously "islanded" portion of Entergy's transmission system south of Lake
Pontchartrain was successfully reconnected to the rest of the company's system.
The innovative operation, later described as "a historic, defining moment" by
Entergy Chairman and Chief Executive Officer Wayne Leonard, was completed by a
cross-functional team from transmission, fossil, system planning and operations,
and nuclear, after Hurricane Gustav heavily damaged key transmission lines in
the New Orleans area.
The islanded portion of the system was
resynchronized to the grid just before midnight Sept. 2, the day after Gustav
slammed into the Louisiana coast at Cocodrie, separating the Amite-South
transmission grid and three fossil units from the rest of the system, and
causing 850,000 outages, the second most in Entergy's history. A second tie was
made minutes later, further stabilizing the grid.
The ties restored the integrity of the
southeastern Louisiana transmission system and made it possible for workers to
carefully begin restoring load and additional generation for the area. That
process continues today.
"This restoration event was critical to the
overall restoration effort and is unprecedented on the Entergy system," said
George Bartlett, director, transmission operations. "It made it possible to
immediately restore high-priority loads such as hospitals, pumping stations,
courthouses, television stations and other key infrastructure."
Earlier, unacceptable test results forced the
project team to abandon its first attempt to reconnect the area, from the
Michoud site in eastern New Orleans. As bad weather continued to plague the
region, the team on the ground moved their equipment a few miles to the
Almonaster site. There, they hoped to take advantage of new, gas breakers for
synchronizing purposes.
Once set up at Almonastor, an engineer called
out readings on the synchroscope while a Michoud operator prepared to close the
breaker at "12 o’clock high" on the synchroscope, a device that displays on a
clock-style face whether power networks and generators can be safely connected.
At the same time, connected by telephone conference call, a Waterford 1 & 2
operator was picking up and dropping load on Unit No. 1 at the engineer’s
command, in an effort to get the synchroscope turning slowly in the clockwise
direction. While Waterford Unit 1, one of three islanded generation units, was
adjusted in this way, the other two, Ninemile Unit 5 and Little Gyspy Unit 2,
were held steady and in manual operation.
"In Jackson, and at other sites, team members
gathered around the phone to hear the countdown to closing the breaker. I think
everyone held their breath as the engineer called out '3 o’clock, 6 o’clock, 9
o’clock, and gave a final brief count, and then the systems were back on line,"
Bartlett said.
|